EGC Construction served as the General Contractor for the Phase 6, Tank 5 Project. This endeavor involved the installation of a new 1.8 million-gallon jet fuel tank, along with associated mechanical piping and sitework. During the project, EGC encountered a significant challenge: contaminated soil, which caused a delay of several months. Collaborating closely with the client and engineer, EGC devised effective solutions to remove the unsuitable soil and proceed with the work. Additionally, EGC navigated numerous existing utilities to successfully install the underground fuel piping. Our trusted subcontractors, including TJ Dyer, Complete Mechanical Services, Knose Concrete, and Bray Construction, played a crucial role in the project's success.